Item Coversheet

BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT

Item No. 6.B.
For Meeting of: AprilĀ 4, 2023

ITEM TITLE:Project Completion and Acceptance for Merrell Bros Inc Project 2561 Biosolids Removal and Reuse
SUBMITTED BY:

Scott Schafer, Director of Public Works

*Mike Price, Wastewater/Stormwater Division Manager (509) 249-6815

SUMMARY EXPLANATION:

City of Yakima (City) Project 2561 dredged, dewatered, and transported 1,709 dry tons of residual Class B biosolids for beneficial use from the Wastewater Treatment Plant's centrate lagoon to restore required lagoon capacity. 

 

Final inspection for this project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue.  A final payment of $58,247.27 is due from the City to Merrell Bros Inc for the completion of the work.

 

Project Manager: Dana Kallevig

Contractor: Merrill Bros, Inc.

Contract Award:  $1,362,650.00

Final Contract Cost: $1,164,945.30 

Retainage Due: $58,247.27

 

The total contract is for the construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept project
ATTACHMENTS:
DescriptionUpload DateType
Completion Letter10/25/2022Backup Material