City of Yakima (City) Project 2548 replaced 2,011 feet of deficient clay and concrete sewer pipe and 9 failing manholes at 8 locations in the City to reduce groundwater infiltration and improve collection system reliability and maintainability.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue. A final payment of $28,582.83 (5% retainage) is due from the City to Hurst Construction, LLC. for the completion of the work.
Project Manager: Dana Kallevig
Contractor: Hurst Construction, LLC.
Contract Award: $699,961.50
Final Contract Cost: $571,656.51
Retainage Due: $28,582.83
The total contract is for the construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |