ITEM TITLE:Project Completion and Contract Acceptance for MBI Construction Services Inc of the Henry Beauchamp JR Community Center HVAC Improvement Project 2551
SUBMITTED BY:

Scott Schafer, Director of Public Works

* Bill Preston, PE, City Engineer (509) 576-6674

SUMMARY EXPLANATION:

MBI Construction Services Inc completed the Henry Beauchamp JR Community Center (HBJCC) HVAC Improvement Project 2551.

 

Final inspection for this project was made and the recommendation is that the project be accepted.  A final payment of $0 is due from the City to MBI Construction Services Inc for the completion of this project.

 

Project Manager: Kerry Jones

Contractor: MBI Construction Services Inc 

Contract Awarded on: 07/07/21

Contract Cost: $118,280.93

Total Due: $0

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Neighborhood and Community Building
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept Project