ITEM TITLE:Project completion and contract acceptance for N 1st St. Phase 3 Revitalization Project Building Demolition at 1st St. and H St. Project 2580
SUBMITTED BY:

Scott Schafer, Director of Public Works
Bill Preston, City Engineer - (509) 576-6754

SUMMARY EXPLANATION:

City Project #2580 provided for work on the 1st St. Phase 3 Revitalization project. The work involved the demolition of the existing building structure at the northeast corner of N. 1st Street and E. ‘H’ Street (803 N. 1st Street), tree removal, and paving of the building footprint area. The City contracted with Russell Crane Service Inc. 

 

Final inspection for this project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment.  A final payment of $3,892.83 (5% retainage) is due from the City to Russell Crane Service Inc for the completion of the work.

 

Project Manager: Randy Tabert

Contractor: Russell Crane Service Inc

Contract Awarded: $84,498.91

Contract Cost: $84,318.64

Retainage Due: $3,892.83

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept Project
ATTACHMENTS:
DescriptionUpload DateType
Project Completion6/28/2022Backup Material