TTC Construction LLC completed the 30-inch transmission main valve installation Project AC2533.
The valve installation was completed as part of the City's Water Division's overall 1st level reservoir rehabilitation project, located at N 40th Avenue and Englewood Avenue. This new valve will allow the reservoir to be taken out of service for a period of time while keeping the 30-inch transmission main in service, providing for improved reliability in our water system operation. The repairs to the 1st level reservoir is anticipated to take place fall/winter of 2022/2023.
Final inspection for this project was made and the recommendation is that the project be accepted. A final payment of $4,640.00 (5% retainage) is due from the City to TTC Construction LLC for the completion of this project.
Project Manager: Mike Shane
Contractor: TTC Construction LLC
Contract Awarded on: 11/16/21
Contract Cost: $100,502.40
Total Due: $4,640.00
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |