City of Yakima (City) Project 2526 replaced 1,000 linear feet of failing hot water supply and return pipe for the treatment plant's anaerobic industrial wastewater treatment system.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue. A final payment of $0 is due from the City to Industrial Construction of Washington LLC for the completion of the work.
Project Manager: Marc Cawley
Contractor: Industrial Construction of Washington LLC
Contract Awarded: 4/6/2022
Payments: $283,785.33
Retainage Due: $0
The total contract is for the construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |