Item Coversheet

BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT

Item No. 4.B.
For Meeting of: December 7, 2021

ITEM TITLE:Project Completion and Acceptance for Instituform Technologies, LLC. - Project 2495  Cured In Place Pipe Rehabilitation of Sanitary Sewer Mains
SUBMITTED BY:

Scott Schafer, Director of Public Works

David Brown, Assistant Director of Public Works

Mike Price, Wastewater/Stormwater Division Manager - (509) 249-6815

SUMMARY EXPLANATION:

City Project 2495 rehabilitated approximately 15,500 linear feet of deficient clay and concrete sewer pipe to reduce groundwater infiltration and improve collection system reliability and maintainability.  The City contracted with Insituform Technologies, LLC. for the improvements using cured-in-place pipe lining technology to minimize surface disturbances.

 

Final inspection for this project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue.

 

Project Manager: Dana Kallevig

Contractor: Insituform Technologies, LLC.

Contract Cost: $808,338.01

Contract Paid to Date: $808,338.01

Retainage Due (project bonded in lieu of retainage): $0

 

The total contract is for the construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept project
ATTACHMENTS:
DescriptionUpload DateType
final10/27/2021Backup Material