City Project SC2581 replaced a total of 150 linear feet of sanitary sewer pipe in the vicinity of Summitview and North 31st Avenue that was not accessible nor maintainable in its current condition; creating a public safety concern. Immediate replacement of the sanitary sewer pipe was required. The project included surface restoration.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $5,395.50 (5% retainage) is due from the City to TTC Construction, Inc. for the completion of the work.
Project Manager: Marc Cawley
Contractor: TTC Construction, Inc.
Contract Cost: $62,602.98
Contract Paid to Date: $57,207.48
Retainage Due (5% of contract cost less tax): $5,395.50
City Council action is required to accept the project and approve the final construction costs. |