City Project #2529 provided for Bravo Company Municipal Solid Waste (MSW) and Wood Debris Removal project. This project was approved by City Council by Resolution R-2020-122 and consisted of excavation of municipal solid waste and wood waste, backfilling with clean material and remediation measures as required to protect groundwater and other environmental measures in the vicinity of Bravo Company Boulevard, as well as the East-West Corridor and I- 82 ramps. Yakima County provided the inspection of the project.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $0 is due from the City to Halme Construction Inc for the completion of the work.
Project Manager: Bill Preston
Contractor: Halme Construction Inc
Contract Awarded: 10/20/2020
Contract Cost: $ 13,539,487.40
Retainage Due: $ 0
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |