Item Coversheet

BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT

Item No. 6.D.
For Meeting of: March 15, 2022

ITEM TITLE:Project completion and contract acceptance for 64th Ave & Ahtanum Rd Project 2474
SUBMITTED BY:

Scott Schafer, Director of Public Works
Bill Preston, City Engineer

SUMMARY EXPLANATION:

City Project #2474 provided for the 64th Avenue and Ahtanum Road Intersection Improvements. The City contracted with ESD Development LLC dba ESF Solutions LLC to provide the improvements which included installation of a traffic signal system, new sidewalk, curb and gutter, and repaving with striping, traffic markings, and signage.  

 

Final inspection for this project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment.  A final payment of $0 (no retainage) is due from the City to ESF Solutions for the completion of the work.

 

Project Manager: Randy Tabert

Contractor: ESF Solutions LLC

Contract Awarded: 09/25/2020

Contract Cost: $529,702.82

Retainage Due: $ 0

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept Project
ATTACHMENTS:
DescriptionUpload DateType
Completion Letter11/29/2021Backup Material
Final Estimate11/29/2021Backup Material