City Project 2109E replaced a total of 350 linear feet of failed 6-inch diameter concrete sewer pipes at 20th Ave/Nob Hill Blvd and at 23rd Ave/Lincoln Ave with 8-inch PVC pipe. The project included repaving of affected roadway.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $8,100.60 (5% retainage) is due from the City to TTC Construction, Inc. for the completion of the work.
Project Manager: Marc Cawley
Contractor: TTC Construction, Inc.
Contract Cost: $175,458.94
Contract Paid to Date: $167,358.34
Retainage Due (5% of contract cost less tax): $8,100.60
City Council action is required to accept the project and approve the final construction costs. |