Item Coversheet

BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT

Item No. 4.I.
For Meeting of: October 19, 2021

ITEM TITLE:Project Completion and Acceptance for TTC Construction, Inc. - Project 2109E 20th Avenue Sewer Line Replacement
SUBMITTED BY:

Scott Schafer, Director of Public Works

David Brown, Assistant Director of Public Works

Mike Price, Wastewater/Stormwater Division Manager - (509) 249-6815

SUMMARY EXPLANATION:

City Project 2109E replaced a total of 350 linear feet of failed 6-inch diameter concrete sewer pipes at 20th Ave/Nob Hill Blvd and at 23rd Ave/Lincoln Ave with 8-inch PVC pipe.  The project included repaving of affected roadway.

 

Final inspection for this project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $8,100.60 (5% retainage) is due from the City to TTC Construction, Inc. for the completion of the work.

 

Project Manager: Marc Cawley

Contractor: TTC Construction, Inc.

Contract Cost: $175,458.94

Contract Paid to Date: $167,358.34

Retainage Due (5% of contract cost less tax): $8,100.60

 

City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:NA
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept project
ATTACHMENTS:
DescriptionUpload DateType
emergency justification10/14/2021Cover Memo
Final9/7/2021Backup Material