City Project # WP2525 replaced the six gates and six automatic gate actuators that control flow through the wastewater treatment plant’s ultraviolet (UV) disinfection system. The project also constructed a catwalk for safe access to the new effluent gates and actuators.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $8,923.40 (5% retainage) is due from the City to TML Construction Inc for the completion of the work.
Project Manager: Marc Cawley
Contractor: TML Construction Inc
Contract Awarded: 1/12/2021
Contract Cost: $ 193,280.84
Retainage Due: $ 8,923.40
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |