City Project # SW2522 installed 2,200 linear feet of new storm drain collection pipe in Arlington Avenue from South 50th Avenue to South 56th Avenue to alleviate re-occurring flooding during rain events. The project also constructed 150 linear feet of new storm drain pipe, one catch basin, and curb and gutter improvements at Skyline Way to improve surface drainage.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $15,299.19 (retainage) is due from the City to TTC Construction Inc. for the completion of the work.
Project Manager: Randy Meloy
Contractor: TTC Construction Inc
Contract Awarded: 1/15/2021
Contract Cost: $ 305,983.78
Retainage Due: $ 15,299.19
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |