City Project SC2487A provided Phase A of the Fair Avenue Sanitary Sewer Conveyance Improvements to serve a fully developed Mill Site. The City contracted with Hurst Construction, LLC. for the replacement of 1,540 linear feet of existing 8-inch diameter sewer main with 15-inch diameter main along Fair Avenue between East Spruce Street and East Beech Street. The project also reconstructed the existing roadway, sidewalk, and curb and gutter.
Final inspection for this project was made and the recommendation is that the project be accepted. Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment. A final payment of $55,882.06 (5% retainage) is due from the City to Hurst Construction, LLC. for the completion of the work.
Project Manager: Dana Kallevig
Contractor: Hurst Construction, LLC.
Contract Cost: $1,209,951.54
Contract Paid to Date: $1,154,069.48
Retainage Due (5% of Contract Cost less tax): $55,882.06
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |