City Project WF2484 installed digester gas drying equipment and a separate digester gas chiller unit. The City contracted with Pease & Sons, Inc. for the digester gas improvements.
Final Inspection for this project was made and the recommendation is that the project be accepted.
Project Manager: Dana Kallevig
Contractor: Pease & Son's, Inc.
Contract Award: 6/12/2019
Contract Cost: $377,655.47
Total Due: $0.00
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project. |