City Project 2469 provided for the construction of stormwater infiltration facilities that will help alleviate chronic flooding due to intense rainfall events at various locations.
Final inspection for this project was made and the recommendation is that the project be accepted. A final payment of $50,282.88 (5% retainage) is due from the City to Wheeler Excavation, LLC for the completion of the stormwater projects.
Project Manager: Randy Meloy
Contractor: Wheeler Excavation, LLC
Contract Awarded: 2/21/2019
Contract Cost: $1,005,657.55
Retainage Due: $50,282.88
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs.
|