On July 17, 2018, the City entered into an agreement with JUB Engineering, Inc. to rehabilitate approximately 22,000 square yards of asphalt pavement, associated drainage, aircraft tie-downs, pavement marking and apron lighting on the Yakima Air Terminal-McAllister Field's West General Aviation Apron. This project was slated to be completed in Fall 2018 where unforeseen weather conditions were not conducive to completing the project prior to the asphalt plants closing. It was recommended to delay construction activities until May 2019 where the project was constructed and has had minimal impacts to Alaska Airlines and surrounding airport tenants.
The amendment addresses a minor increase in wage rates set by JUB Engineering, Inc. for their 2019 calendar year. The increase, not to exceed $12,480, has been approved by the Federal Aviation Administration and is therefore eligible to be reimbursed under the federal grant and local passenger facility charge program.
This contract amendment will not impact the City's general or reserve funds. |