ITEM TITLE:Project Completion and Contract Acceptance for Knobel's Electric, Inc. - Project 2414, Randall Park Improvements
SUBMITTED BY:

Scott Schafer - Director of Public Works

Bob Desgrosellier - Acting Chief Engineer - 509-575-6228

 

SUMMARY EXPLANATION:

City Project 2414 provided for the completion of improvements at Randall Park. The City contracted with Knobel's Electric, Inc. for constructing improvements within the east parking lot, including new concrete curbing, ADA ramps, sidewalk, and installation of pole bases for lighting.   

 

Final inspection for this project was made and the recommendation is that the project be accepted.  A final payment of $2,266.65 (5% retainage) is due from the City to Knobels Electric, Inc. for the completion of the improvement work at Randall Park.

 

Project Manager: Bruce Floyd

Contractor: Knobel's Electric, Inc.

Contract Awarded: 4/20/2018

Contract Cost: $49,050.31

Retainage Due: $2,266.65

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.


ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Neighborhood and Community Building
APPROVED FOR SUBMITTAL: City Manager
STAFF RECOMMENDATION:
Accept Project
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
DescriptionUpload DateType
Final4/17/2019Cover Memo