ITEM TITLE:Project Completion and Contract Acceptance for Scout Lake Construction, Inc. - Project 2365 Beech Street Interceptor
SUBMITTED BY:

Scott Schafer, Director of Public Works 

Mike Price, Wastewater/Stormwater Manager 249-6815

 

SUMMARY EXPLANATION:

City Project 2365 provided for improvements to the Beech Street Interceptor.  The City contracted with Scout Lake Construction, Inc. for the construction of 60 LF of 15-inch gravity sewer main and 2,950 LF of 24-inch gravity sewer main with manholes and appurtenances, removal of an existing structure, connection to the existing sanitary sewer collection system, and a temporary sewage bypass, and restoration. 

 

Final inspection for this project was made and the recommendation is that the project be accepted.  A final payment of $52,978.49 (5% retainage) is due from the City to Scout Lake Construction, Inc. for the completion of the scope of work associated with the Beech Street Interceptor. 

 

Project Manager: Dana Kallevig

Contractor: Scout Lake Construction, Inc. 

Contract Award: 5/11/2017

Contract Cost: $1,146,454.50

Retainage Due: $52,978.49

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Economic Development
APPROVED FOR SUBMITTAL: City Manager
STAFF RECOMMENDATION:
Accept Project
BOARD/COMMITTEE RECOMMENDATION:
ATTACHMENTS:
DescriptionUpload DateType
Final12/21/2018Cover Memo