For Meeting of: JuneĀ 5, 2018

ITEM TITLE:Project completion and project acceptance for Boise River Fence, Inc. - 2018 Security Gate Improvements (Standard Motion V-B-Accept the project and approve)
SUBMITTED BY:Robert K. Peterson, Airport Director, 509-575-6149
SUMMARY EXPLANATION:

City Project 2017-141 provided for the upgrade in security infrastructure throughout the Yakima Air Terminal-McAllister Field.  The City contracted Boise River Fence, Inc. to replace 11 automatic vehicle access gates, 9 pedestrian gates, improve ADA compliance, and install flood lighting.  Staff recommends that the project be accepted and a final payment of $34,317.34 (retainage) be provided to Boise River Fence, Inc. for completion of these security improvements. 

 

Project Manager: Mike Uhlman, HLA Engineering and Land Surveying, Inc.

Contractor: Boise River Fence, Inc.

Contract Date: August 25, 2017

Contract Award: $743,388.10

Retainage Due: $34,317.34

 

The total contract cost reflects construction only and does not include engineering and other associated costs.  City Council action is required to accept the project and approve final construction payment. 

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL: City Manager
STAFF RECOMMENDATION: