ITEM TITLE:Project Completion and Contract Acceptance for Knobels Electrical Inc. - Project 2407 Capitol Theatre Dimmer (Standard Motion V-B-Accept the project and approve)
SUBMITTED BY:

Brett Sheffield - Chief Engineer 575.6797

Scott Schafer, Public Works Director

SUMMARY EXPLANATION:

City Project 2407 provided for the installation of the Capitol Theatre Dimmer System Modification.  The project consisted of revision of the stage lighting system, raceway conduits, fittings, boxes, hangers, connectors, couplings, and other accessories as necessary.  The City contracted with Knobel's Electric, Inc. to perform the specialized work on the project. Final inspection for this project was made and the recommendation is that the project be accepted.  A final payment of $1,797.20 (5% retainage) is due from the City to Knobel's Electric, Inc. for the completion of the work.

 

Project Manager: Bob Desgrosellier

Contractor: Knobel's Electric, Inc.

Contact Awarded: 5/16/2017

Final Contract Payment (5% Retainage) Due: $1,797.20

Total Contract Cost: $38,891.41

 

The above total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Trust and Accountability
STAFF RECOMMENDATION:
Accept the project