ITEM TITLE:Amend North First Street Project Design and Phasing
SUBMITTED BY:

Joan Davenport, Community Development Director

Brett Sheffield, Chief Engineer

Debbie Cook, Director of Engineering and Utilities

SUMMARY EXPLANATION:

The North First Street Revitalization project is a City Council Economic Development priority. Construction funding will be provided from a combination of Federal Surface Transportation Program (STP) funds and a City Council issued bond. This report recommends a slight modification in the construction sequencing and design layout for the street corridor.

 

Construction sequencing of the North First Street Revitalization project will begin at Martin Luther King Jr. Boulevard to "I" Street; the next construction phase will be "I" Street to "N" Street, then the final construction sequence will be "N" Street to I-82.

 

Bicycle facilities will include buffered bike lanes in both directions on North First Street between MLK Jr Blvd and "I" Street. No bike lanes will be constructed north of "I" Street. Cyclists will be directed on "I" Street to either North 6th Avenue or North 4th Street, both of which connect to the Yakima Greenway.

Resolution: Ordinance:
Other (Specify): 
Contract: Contract Term: 
Start Date: End Date: 
Item Budgeted: Amount: 
Funding Source/Fiscal Impact:Council Issued Street Bond of approximately $8 Million. Additionally, $2.7 Million Federal Surface Transportation Program Funds are dedicated to this project, but have been delayed until 2019.
Strategic Priority:Economic Development
Insurance Required? No
Mail to: 
Phone:
APPROVED FOR SUBMITTAL:City Manager
RECOMMENDATION:
Accept report
ATTACHMENTS:
DescriptionUpload DateType
Amend North First Street Design and Phasing11/6/2015Backup Material