This project (City Project.: 2267C) a final payment of $65,981.76 is recommended for the constructed of a new concrete box diversion structure, two new concrete discharge structures, two parallel 42 inch pipes totaling approximately 3,000 linear feet in length, two open conveyance channels and side channels within the riparian area of the City of Yakima Wastewater Treatment Plant.
Final inspection for this project was made and the recommendation is that the project be accepted.
This Council action is to accept the project and approve the final construction costs.
Project Manager: Jeremy Hoover
Contractor: Strider Construction Co. Inc.
Contract Awarded: 8/4/2014
Contract Cost: $1,427,845.34
Retainage Due: $65,981.76
The above total contract cost is for construction only and does not include engineering and other costs.
|