Item No. 5.C.
For Meeting of: September 1, 2015

ITEM TITLE:Project Completion and Contract Acceptance for Strider Construction Co, Inc. - Project 2267C Yakima Floodplain Restoration Outfall Alternative PH II (Standard Motion V-B-Accept the project and approve)
SUBMITTED BY:

Debbie Cook - Director of Utilities and Engineering - 509-575-6120

Jeremy Hoover, P.E. - Pretreatment Supervisor - 509-424-2589

 

SUMMARY EXPLANATION:

This project (City Project.: 2267C) a final payment of $65,981.76 is recommended for the constructed of a new concrete box diversion structure, two new concrete discharge structures, two parallel 42 inch pipes totaling approximately 3,000 linear feet in length, two open conveyance channels and side channels within the riparian area of the City of Yakima Wastewater Treatment Plant.

 

Final inspection for this project was made and the recommendation is that the project be accepted.

 

This Council action is to accept the project and approve the final construction costs.

 

Project Manager: Jeremy Hoover

Contractor: Strider Construction Co. Inc.

Contract Awarded: 8/4/2014

Contract Cost: $1,427,845.34

Retainage Due: $65,981.76

 

The above total contract cost is for construction only and does not include engineering and other costs.

 

Resolution: Ordinance:
Other (Specify): Project Completion and Contract Acceptance
Contract: Contract Term: 
Start Date: End Date: 
Item Budgeted: Amount: 
Funding Source/Fiscal Impact:Wastewater
Strategic Priority:
Insurance Required? No
Mail to: 
Phone:
APPROVED FOR SUBMITTAL:City Manager
RECOMMENDATION:
Accept Project