The City of Yakima selected Apollo Inc. as the contractor on Resolution R-2023-125 for the N 1st Street Phase 3 Project 2580. Additional work was required of Apollo Inc. due to the discovery of a large box culvert and encased pipe within the roadway. While excavating for the installation of water services, these unknown obstructions were encountered.
The total cost of Change Order 2 is $120,000.00 and would increase the number of working days by 15. |