The existing roof on the Henry Beauchamp Jr. Community Center (HBJCC) is failing, has experienced leaking over the past few years, and is in need of replacement. Project 2798 entails the removal and replacement of the roof along with improvements to the drainage system.
M.G. Wagner Company Inc. was the low bidder at $195,743.59 and determined to be qualified to perform the necessary construction work.
Enclosed for City Council review is the Agreement with M.G. Wagner Company Inc. in the amount not to exceed $195,743.59. The project is being funded by REET 1 funds. |