Item Coversheet

BUSINESS OF THE CITY COUNCIL
YAKIMA, WASHINGTON
AGENDA STATEMENT

Item No. 7.H.
For Meeting of: May 21, 2024

ITEM TITLE:Resolution authorizing an agreement with M.G. Wagner Company Inc for the Henry Beauchamp Jr. Community Center Re-Roofing Project 2798
SUBMITTED BY:

 Scott Schafer, Director of Public Works

* Kerry Jones, Fleet and Facility Manager

SUMMARY EXPLANATION:

The existing roof on the Henry Beauchamp Jr. Community Center (HBJCC) is failing, has experienced leaking over the past few years, and is in need of replacement.  Project 2798 entails the removal and replacement of the roof along with improvements to the drainage system.

 

M.G. Wagner Company Inc. was the low bidder at $195,743.59 and determined to be qualified to perform the necessary construction work.  

 

Enclosed for City Council review is the Agreement with M.G. Wagner Company Inc. in the amount not to exceed $195,743.59.  The project is being funded by REET 1 funds.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Public Safety
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Adopt Resolution.
ATTACHMENTS:
DescriptionUpload DateType
Resolution Wagner HBJCC Roof5/3/2024Resolution
M.G. Wagner HBJCC Roof Contract4/24/2024Contract