| City Project #2566 provided for the milling and overlaying of approximately 1.63 miles of roadway and ADA curb ramp improvements on Summitview Avenue from 40th Ave. to 48th Ave. and 56th Ave. to 72nd Ave. Final inspection for the project was made and the recommendation is that the project be accepted.  Project completion is subject to issuance of Certificate of Payment by the Department of Revenue and authorizations from state agencies allowing final payment.  A final payment of $0 is due from the City to the contractor for the completion of the work.   Contractor: Central Washington Asphalt Inc Total Contract Cost: $2,134,993.75 Retainage Due: $0   The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs. |