City of Yakima (City) Project WP2631 rehabilitates two of the four primary clarifiers at the wastewater treatment plant. The clarifiers were constructed in 1936 and were most recently rehabilitated in 1996. The Project will replace all clarifier mechanical components, repair and resurface the clarifier concrete surfaces, and line several of the attached pipes.
The City utilized the procedure established by the State of Washington for competitively bidding projects. Three contractors submitted bids, with Prospect Construction, Inc. submitting the lowest bid of $4,102,380. The Contract is attached for City Council review. Funds are budged from Wastewater Capital Fund 472. |