Hancock Sandblast & Paint LLC completed the Naches River Water Treatment Plant Effluent Flume Concrete Repair Project AC2601. Final inspection for this project was made and the recommendation is that the project be accepted. A final payment of $0 is due from the City to Hancock Sandblast & Paint LLC for the completion of this project.
Project Manager: Mike Shane
Contractor: Hancock Sandblast & Paint LLC
Contract Awarded on: 10/06/22
Contract Cost: $81,972.00
Total Due: $0
The total contract cost is for construction only and does not include engineering and other costs. City Council action is required to accept the project and approve the final construction costs. |