City Quote No. 22204S provided work on the Miller Park Baseball Court Lighting project. The work involved excavation and backfill for the installation of six new concrete bases and lighting poles containing 14 LED fixtures with timers, trench around park to feed lights from existing service cabinet and demo of existing concrete poles and bases.
Final inspection for the project was made and the recommendation is that the project be accepted. Project completion was subject to issuance of Certificate of Payment by the Department of Revenue and authorization from state agencies allowing final payment. A final payment of $2,150.42 (5% retainage) is due from the City to Knobel's Electric, Inc.
Project Manager: Ken Wilkinson
Contractor: Knobel's Electric, Inc.
Contract Award: $46,578.00
Retainage Due: $2,150.42
City Council action is required to accept the project and approve final costs. |