ITEM TITLE:Project Completion and Contract Acceptance for Interwest Construction Inc for the Water Transmission Main Repair EPO #2212E Project AC2655
SUBMITTED BY:

Scott Schafer, Director of Public Works

* David Brown, Assistant Director of Public Works - (509) 575-6204

Mike Shane, Water/Irrigation Engineer

SUMMARY EXPLANATION:

Interwest Construction Inc completed the Water Transmission Main Repair EPO #2212E Project AC2655. The contractor implemented protective measures on the Naches River for the 48-inch water transmission main.  

 

Final inspection for this project was made and the recommendation is that the project be accepted.  A final payment of $8,638.63 (5% retainage) is due from the City to Interwest Construction Inc for the completion of this project.

 

Project Manager: Mike Shane

Contractor: Interwest Construction Inc

EPO Awarded on: 08/08/22

Contract Cost: $181,411.13

Total Due: $8,638.63

 

The total contract cost is for construction only and does not include engineering and other costs.  City Council action is required to accept the project and approve the final construction costs.

ITEM BUDGETED:Yes
STRATEGIC PRIORITY:Neighborhood and Community Building
APPROVED FOR SUBMITTAL BY THE CITY MANAGER
RECOMMENDATION:
Accept Project
ATTACHMENTS:
DescriptionUpload DateType
Final 1/11/2023Backup Material